China News Service, Chengdu, December 24 (Reporter Wang Peng) The reporter learned from the Sichuan Investment Group on the 24th that the Yaxi Expressway Yaoheba Bridge, which was damaged in the collapse of the "9·20" high-level mountain, passed the acceptance check on the same day. The post-disaster reconstruction will be completed and the two-way traffic will be opened at 8 o'clock on the 25th.

The picture shows the reconstruction site after the disaster.

Photo courtesy of Sichuan Trading

  At 11:50 on September 20 this year, a high-level mountain collapse occurred on the right side of the Yaoheba Bridge in the direction of Chengdu to Xichang from the asbestos section of the Yaxi Expressway. About 20,000 cubic meters of rocks broke the right bridge of the Yaoheba Bridge and spread to the left. The two-way traffic on the Shimian-Liziping section of the Yaxi Expressway was interrupted by the bridge piers, and the 108 National Road under the bridge was also interrupted.

The picture shows the recent load test site.

Photo courtesy of Sichuan Trading

  The reporter learned that the post-disaster reconstruction has successively completed the construction of pier pile foundation punching, T beam prefabrication and erection, bridge deck asphalt concrete pavement, marking, standard load test, etc.

As of the 24th, it passed the completion acceptance, and the reconstruction only lasted more than 90 days, which was completed about one and a half months earlier than the original plan.

The picture shows the recent pavement laying.

Photo courtesy of Sichuan Trading

  The Yaxi Expressway is an important section of the Jingkun Expressway in Sichuan and an important passage from Chengdu to Liangshan Yi Autonomous Prefecture. It is of great significance to the poverty alleviation and prosperity of China's Yi ethnic communities.

(Finish)