China News Network, Beijing, February 29th (Wang Yan) The satellite terminal of Beijing Daxing International Airport resumed work. It is reported that after its completion, the annual passenger throughput of Beijing Daxing International Airport will increase from 45 million to 72 million.

The satellite hall is a form of terminal layout, suitable for hub airports with a large number of transit passengers. Many large international airports, such as Orlando Airport and Atlanta Airport, have adopted the satellite hall layout. According to the planning design, the satellite hall of the Beijing Daxing International Airport Terminal is located 667 meters south of the Beijing Daxing International Airport terminal. The overall planning structure is in the east-west “one” shape with a total length of about 1203 meters and a total building area of ​​over 20 Ten thousand square meters.

The reporter learned from Daxing District, Beijing that on the basis of safeguarding the epidemic prevention work, Daxing District proceeded in an orderly manner to resume work and resume production at the construction site. At present, the construction project of Beijing Daxing International Airport is steadily and safely organizing the resumption of work.

Several departments in the Daxing District jointly inspected the prevention and control measures for the living quarters, office areas, construction sites, and other places of the satellite hall project, as well as the prevention and control of epidemic situations such as the setting of isolated areas and preparations for resumption.

Construction site drawing of the satellite terminal of Beijing Daxing International Airport. Photo courtesy of Daxing District, Beijing

Gan Yadi, expert deputy director of the Center for Disease Control and Prevention of Daxing District, said that the project site has met the Beijing Municipal Construction and Construction Commission's requirements for the construction project in terms of prevention and control. To control the epidemic situation and avoid the occurrence of new coronary pneumonia at the construction site. After evaluation, the three parties signed the Joint Inspection Form for Epidemic Prevention on Construction Sites and approved the resumption of work on the site.

After the completion of the satellite hall project of Beijing Daxing International Airport, the annual passenger throughput of Beijing Daxing International Airport will increase from the current 45 million to 72 million. Liu Hanchao, chief technology engineer of Beijing Urban Construction Group, said that the current construction content of the satellite hall project is a partial underground structure project. When the work was stopped before the festival, the engineering piles and earthwork excavation work were completed.

He said that because the main structure of the satellite hall passes through two high-speed rail tunnels, Jingxiong and Jingan paste, the accuracy of the high-speed rail is very high. If the track is laid without first solving the above-ground engineering construction, the accuracy of the high-speed rail will be affected during subsequent construction. Therefore, in order to solve the problems such as the intersection of the ground and the ground during the construction period, it is necessary to start the construction of the foundation and foundation works of the satellite hall in advance to ensure that the ground and underground works can be completed on schedule.

Jiang Luhong, the project manager of the non-main living facilities project of the China Construction Eighth Bureau, said that the Daxing District invited experts in epidemic prevention and control to answer questions on epidemic prevention at construction sites, which will greatly help the project's epidemic prevention work in the future, and will also help A good knowledge reserve was made on the application of epidemic prevention and control and return to work.

Zhang Meng, head of the airport team of the Daxing District Construction and Construction Committee Supervision Station, introduced that as of February 28, there were 255 construction sites in Daxing District, with a total of 5,145 people on site. All construction sites are under closed management, and returnees are required to conduct isolation and observation in designated areas as required. At present, their physical conditions are normal, and no confirmed or suspected cases of new coronary pneumonia have been found. (Finish)