Kyushu's operations were suspended due to heavy rain, and the factory continued to restart at 11:25 on July 8.

Due to heavy rain, operations at plants in Fukuoka and Saga prefectures have been suspended due to blackouts and floods.

Mitsui Chemicals has been shutting down this plant since 6th due to a power outage at its plant in Omuta City, Fukuoka Prefecture.
This means that a substation nearby was inundated, but the plant was not inundated.

Denka, a chemical manufacturer, has been shut down since 6th due to partial flooding at a plant in Omuta City, which manufactures electronic components for automobiles.
It means that we will start the inspection of the equipment on the 8th, and resume the operation one by one when the safety can be confirmed.

Mitsui Mining & Smelting Co., Ltd. has suspended some operations because the factory site in Omuta City has been flooded with water.

On the other hand, three plants in Bridgestone, Fukuoka Prefecture, Kurume City, Fukuoka Prefecture, Asakura City, and Tosu City, Saga Prefecture, which had suspended operations to ensure the safety of employees, although there was no damage, resumed operations from the morning of the 8th. I will.

In addition, Sapporo Beer factory in Hita City, Oita Prefecture, and QP factory in May, Tosu City, Saga Prefecture, such as commercial mayonnaise, have resumed operations.